Germany Faces Five-Year Delay on New K130 Corvette Deliveries
Germany’s second-batch K130 corvettes will be delivered later than promised, with Emden and Köln now due only in 2027, Sicherheit & Verteidigung reported, citing a Rheinmetall presentation.
Choose Clash Report as a preferred source and see our reporting first in Top Stories.
- The five 89-meter boats were ordered in September 2017, with deliveries originally due from 2022 and the batch complete by 2025.
- At the christening of Lübeck on April 29, 2026, Rheinmetall still said Emden and Köln would be handed over this year.
- Costs for the second batch have risen to about €2.4 billion, roughly 21% above the 2017 contract volume, Sicherheit & Verteidigung reported.
The boats, designed for coastal reconnaissance and anti-surface warfare in the North Sea and the Baltic, are the sixth to tenth units of the Braunschweig class.
Sicherheit & Verteidigung, a German defense publication, said a Rheinmetall presentation now puts delivery of the first two ships, Emden and Köln, only in 2027 — about five years behind the original plan.
Five Years Behind the Original Plan
The Federal Office of Bundeswehr Equipment, Information Technology and In-Service Support, or BAAINBw, awarded the second-batch contract in September 2017 to the ARGE K130 consortium.
Fr. Lürssen Werft led the group, with thyssenkrupp Marine Systems and German Naval Yards Kiel as partners. The boats were due to start reaching the navy in 2022, with all five in service by 2025.
Rheinmetall completed its takeover of Naval Vessels Lürssen, or NVL, on March 1, 2026, and has since led the program with the same industrial partners.
That timetable had already slipped when Lübeck, the last ship of the batch, was christened at the Blohm+Voss yard in Hamburg on April 29, 2026 — Rheinmetall’s first ship christening after the NVL deal.
Tim Wagner, chief executive of Rheinmetall’s Naval Systems division, said at the time: “Our focus now turns to the upcoming milestones, which will culminate this year with the delivery to our customer of the two corvettes EMDEN and KÖLN.”
Deutsche Presse-Agentur reported then that Lübeck itself was expected to be handed over in 2028, after outfitting, functional tests and acceptance.
Köln had already gone through a “small flag ceremony” at Blohm+Voss on Sept. 19, 2025, and later sailed to Warnemünde. In a note quoted by MILMAG, NVL said the navy could use Köln and, earlier, Emden for trials and training while work continued toward full operational capability, calling the ceremony a milestone “on the path to delivery.”
Also read: Germany Scraps Multibillion-Euro Plans for Its Biggest Warship Project Since WWII
Combat System Blamed for the Slip
Sicherheit & Verteidigung said difficulties integrating the command and weapons engagement system, or FüWES, which ties the ships’ sensors and weapons into one combat system, are a principal reason for the delay.
In January 2025, t-online, citing Ostsee-Zeitung, quoted an NVL spokesman as pointing to supply-chain bottlenecks and “considerable technical challenges” with the combat system.
The spokesman also cited new information-security requirements, which he said reflected the customer’s changed approach to cybersecurity after the shift in Europe’s security situation.
Costs Rise to About €2.4 Billion
About €1.9 billion had originally been budgeted for the five corvettes. The 2017 construction contract had a financial volume of just under €2 billion, according to BAAINBw, Sicherheit & Verteidigung reported.
Costs now stand at about €2.4 billion, roughly 21% above the contract volume, or about €480 million per ship.
Third Batch Is Dropped
A third batch, intended to replace the five first-batch corvettes that entered service between 2008 and 2013, will not be bought. Sicherheit & Verteidigung said the plan was dropped for technical and financial reasons.
In its 2025 strategy paper “Kurs Marine,” the navy put its requirement at six to nine corvettes, to be supported later by 18 unmanned surface vessels known as Future Combat Surface Systems.
If the first-batch boats remain in service until their planned end of life in 2038, the navy can cover that requirement at least until then once the second batch arrives. It also plans to bring one first-batch ship up to the second-batch equipment standard.
Also read: Rheinmetall Slashes Revenue Forecast Due to Scrapped German Warship Deal
Why It Matters
The delay keeps Germany’s navy short of the extra coastal combatants it ordered for the North Sea and the Baltic, waters that have become more exposed since Russia’s full-scale invasion of Ukraine.
It also adds to a run of German naval procurement setbacks. Berlin this year scrapped the F126 frigate program, a blow to Rheinmetall’s first major push into shipbuilding after it bought NVL.
Until Emden and Köln are formally delivered, the navy must lean on first-batch corvettes and on ships already in its hands only for trials and training. The 2027 date, if it holds, still leaves Lübeck, the last of the five, slated for 2028.
Kamer Kurunç
Kamer Kurunç is the Editor-in-Chief of Clash Report and has led the outlet for four years. Kamer sets the site's editorial direction and writes and edits coverage across the World and Defense sections, with a focus on the Russia-Ukraine war, NATO, Israel and Iran, Türkiye, North Korea and nuclear weapons. Kamer has written more than 1,100 articles for Clash Report.